Watch CBS News

Fix 50 Phase 1 Ahead Of Schedule; Phase 2 To Begin Thursday

SACRAMENTO (CBS13) – Phase 1 of the eastbound Fix 50 work will finish five days early, Caltrans officials announced Wednesday.

Work on Eastbound Phase 2 is now going to begin Thursday evening. The new phase will move traffic from the outside lanes to the inside three lanes. The change-over is scheduled to start around 9 p.m. Thursday, Caltrans says.

If you happen to be trying to get through the area in the early morning, expect traffic breaks after midnight as crews will be working to take down the overhead signs.

By 5 a.m. Friday, the change-over will be complete. Eastbound Highway 50 work is now expected to be completed earlier than May 21, Caltrans says.

Phase 2 will require two on-ramps and two connectors to be closed throughout the work. Expect the following closures: the 11th Street on-ramp, the 16th Street on-ramp, the southbound Highway 99 connector, and the eastbound Business 80 connector.

Work on the westbound side will not being until May 27, after Memorial Day.

View CBS News In
CBS News App Open
Chrome Safari Continue
Be the first to know
Get browser notifications for breaking news, live events, and exclusive reporting.