SACRAMENTO, Calif. (AP) – A document obtained by The Los Angeles Times says the first leg of California’s $64 billion high-speed rail project could cost as much as $3.6 billion more than previous estimates and take years longer to build.

The newspaper says the details are in a confidential Federal Railroad Administration risk analysis.

California High-Speed Rail Authority officials said Friday that it includes outdated information and is being mischaracterized. Businesses and government agencies typically perform risk analyses to assess potential dangers.

Rail Authority CEO Jeff Morales says the agency is constantly working to identify and fix problems before they occur.

The document shows that in a worst-case scenario, it could cost up to $10 billion to build bridges, viaducts, trenches and track on 118 miles from Merced to Shafter, up from $6.4 billion.

Comments
  1. Frank Romo says:

    A waste of taxpayer money for what? Who wants to go to LA from Nor-Cal? Take the bus, drive or fly, spending that kind money could be used for building water reservoirs for the drought we’ve been experiencing, Brown isn’t in touch with reality. He also wants to build 40′ diameter twin water tunnels to send water down to LA, really? What a TOOL!

Leave a Reply

Please log in using one of these methods to post your comment:

Google+ photo

You are commenting using your Google+ account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

w

Connecting to %s